Practical Risk Management for EPC / Design-Build Projects. Walter A. Salmon

Читать онлайн книгу.

Practical Risk Management for EPC / Design-Build Projects - Walter A. Salmon


Скачать книгу
risks materialising.

      I do not pretend that the advice in my book is intended to be a balanced document equally reflecting the interests of both parties to an EPC or Design-Build Contract (i.e. both the Employer and the Contractor). On the contrary, I have written primarily for the benefit of Contractors. I have therefore deliberately avoided mentioning situations where the Employer could take advantage of the Contractor. Having said that, nowhere do I make any suggestions that amount to the Contractor ripping off the Employer; but putting the Contractor into a legitimately stronger position, most certainly ‘yes’. The purpose of my book is simply to show where managing the risks better will prevent unnecessary losses for the Contractor. Of course, nothing prevents a member of the Employer's Team from reading this book, learning where the Contractor is most likely not to be managing risks properly, and then using that knowledge to defeat the Contractor's claim for extra time and/or money. The way for Contractors to overcome that problem is for them to sharpen up their Project Risk Management capabilities.

      I included the term ‘Design-Build’ in the title of this book, since I consider that there are only subtle differences between how EPC Projects and Design-Build Projects are set up and run. The reality is that the risks I cover in this book can apply equally to both types of Project since, under each of the different arrangements, the responsibility for the design work (as well as the procurement and construction work typical to all construction Projects) falls to the Contractor. I have therefore opted in later chapters not to repeat the term ‘Design-Build’ unless I felt it was particularly necessary to do so.

      1 an incomplete Conceptual Design;

      2 an outline Functional Specification that requires finalisation during the bid negotiation phase (i.e. no detailed specifications are provided);

      3 a preliminary Plot Plan (i.e. not a fixed layout) that likewise needs to be firmed up in the bid negotiation period;

      4 a mixed complement of loosely coordinated technical and administrative requirements that contain many references to third-party standards that sometimes conflict with each other; and

      5 a set of contractual requirements that are heavily biased in the Employer's favour.

      I have had a number of people who have read some of my observations of where things went wrong on construction projects say words to the effect of ‘it's just bad management’, as if telling people to employ ‘good management’ would have miraculously cured the problems I encountered. My stance is that the many people I observed suffering the negative effects of their own poor management were usually completely unaware of what they had done wrong (or had failed to do correctly). Knowing that you have to employ good management is very different from knowing what good management is. The purpose of this book is therefore to divulge what I myself have seen go wrong, and to offer my advice as to how such situations could have been handled better. My hope is that this will lead to sound Project Risk Management being put into practice more often.

      

      The principal negative comments against the EPC approach I received were as follows:

      1 Too many Contractors working on EPC Projects have failed miserably to achieve the time and cost objectives. As McKinsey & Company found in 2017, Project durations have often been horribly extended and the final costs have quite regularly far exceeded the original budgets.6(This does not appear to be as big an issue for Design-Build Projects, perhaps because their application is often to much smaller undertakings (private residences being an example). Such Projects are also often carried out by highly specialised teams with tried-and-tested technology [for example, cold storage building contractors, swimming pool installers and prefabricated building suppliers]. In such cases, the risk sharing between the Contractor and the Employer seems to be much more evenly balanced than on EPC Projects [especially when compared to the fixed-price, major turnkey ones], as was observed by Banik and Hannan.7 )

      2 The Contractor is responsible for and has complete control over at least the detailed design work, and may therefore be tempted to skimp on the quality of the finished facility wherever it


Скачать книгу