Practical Risk Management for EPC / Design-Build Projects. Walter A. Salmon

Читать онлайн книгу.

Practical Risk Management for EPC / Design-Build Projects - Walter A. Salmon


Скачать книгу
conducted reasonably extensive investigations into the above points to see if the Employers' suppositions held water, but my attempts at proving the efficacy (or otherwise) of the EPC approach over the Traditional Contracting route only turned up the following.

      1 Construction Projects worldwide notoriously do not finish on time.9 However, I could not determine whether or not EPC Projects finish closer to their original completion time than Projects implemented using the Traditional Contracting route, simply because I could not unearth any comparative data on the topic.

      2 Likewise, I was not able to find any evidence to show whether or not Projects conducted under an EPC arrangement are less affected by increased costs for the Employer than those conducted under the Traditional Contracting approach.

      3 When it comes to data showing that, in terms of quality and reliability, the completed facility resulting from EPC Projects is as good as or worse than that seen in Projects completed via the Traditional Contracting route, nothing seems to be available there either.

      Since I could find no data to counter the abovementioned supposed benefits of EPC Contracts from the Employer's perspective, I have no reason to consider that the Employer's viewpoint might be wrong. In addition to the foregoing, it also seems that Employers very much like the fact that the EPC Contractor offers them a single point of contact (‘one-stop shop’) for everything on the Project. That is not just for the guaranteeing of the efficacy of the design and construction work but also for allocating total responsibility in the event that something goes wrong at any stage, whether it is with design, procurement, construction, or post-completion operations. A further added benefit for Employers is that many of the risks that would ordinarily fall to the Employer to bear can legitimately be transferred to the Contractor under the EPC Contract (at a price, of course), simply because the Contractor is given the entire Project implementation responsibility. That could never be the situation under the Traditional Contracting route.

      On the other hand, under an EPC Project, if the extension of time for completion of the Project is not caused by an excusable delay, the Contractor has to bear the associated additional cost burden as well as compensate the Employer (by way of Liquidated Damages) for completing the Project late. I can therefore fully appreciate why Employers nowadays will want to turn more and more to undertaking new complex Projects on a lump-sum EPC basis, rather than rely on the Traditional Contracting route. All this is not good news for Contractors since, as I have just mentioned, the risks placed upon them are far greater with lump-sum EPC work than where some other entity is responsible for undertaking the design work. For the majority of EPC Projects, those increased risks tend to make it harder for the Contractors to achieve the originally intended level of profit.

      Sometimes, the Conditions of Contract proffered by the Employer for EPC Projects may contain the words ‘fixed-price’ as well as the term ‘lump-sum’; I have seen that this combination of words can hurt the Contractor. I say this, because I experienced a number of instances where the Employer's Team took the position that those additional words meant that the Contractor could not claim any additional money over and above the original Contract Price under any circumstances whatsoever. That position ignored the fact that there were many clauses in the Contract that mentioned the right of the Contractor to be reimbursed for extras arising from the Employer's side.

      My advice to the Contractor regarding these unacceptable (and added risk) situations is twofold:

      1 Never accept the words ‘fixed price’ in the Conditions of Contract, and most certainly not in conjunction with the phrase ‘lump-sum’.

      2 Always insist that adequate clauses are added that will entitle the Contractor to reimbursement for Employer-directed Variations. This is especially so if the Employer is adamant that such clauses are missing because no Variations will be allowed (which should be regarded by the Contractor as a ‘red flag’ that major problems are sitting just over the horizon).

      In an effort to select the best Contractor for an EPC Project, the Employer will normally issue a suite of appropriate bidding (tender) documents to a group of prequalified construction-focused bidders that are highly experienced in, and can demonstrate satisfactory execution of, EPC work. Those bidding documents set out the specific requirements of the Employer for the work to be performed, as well as the requirements for the end outputs from the completed facility. The bidding process itself is frequently divided into two distinctly separate parts (the Technical Bid Proposal and the Commercial Bid Proposal), where the Employer will not proceed with considering a Commercial Bid Proposal until the corresponding Technical Bid Proposal has been found to be acceptable.

      The Contractor's preparation work for its Bid Proposals will usually be undertaken under the direction and control of its Proposal Department, and it will also involve a range of different people from the company's corporate workforce (i.e. personnel who are part of the main office's permanent staff and who will not usually be allocated to work on any specific Projects). A tremendous amount of work


Скачать книгу