Practical Risk Management for EPC / Design-Build Projects. Walter A. Salmon

Читать онлайн книгу.

Practical Risk Management for EPC / Design-Build Projects - Walter A. Salmon


Скачать книгу
because the responsibility for handling such issues should fall to specialists in the area of financial and legal matters, and not to the members of the Project Implementation Teams.Sadly, however, it is often management of the corporate risks where Contractors fall down. Too often, therefore, workers have unexpectedly found themselves out of a job due to the incompetence of their Corporate Management Team and/or Board of Directors, and without any financial cushion to tide them over until a new job comes along. Worse still, it is not unknown for Directors to have received bonuses (or have still been expecting them) even as they walked away from the bankruptcy that their incompetence may well have created.4

      2 The Project Implementation RisksThese are the particular risks specific to implementing each of the Projects that the Contractor is handling, and which are predominantly the responsibility of the individual Project Managers and their associated Department Managers to handle.5 Those are the risks that this book is principally focused on.

      If the Employer also insists on an unusually short time-frame for completion (with substantial Liquidated Damages payable by the Contractor if the Project is completed late), then truly effective management of the risks involved becomes an absolutely essential task for the Contractor to perform if the Contractor's expected profit is going to have any chance of being achieved. The Employer will inevitably be very strict on adherence to the completion date in the situation where the Employer is liable to pay heavy penalties to any third parties in the event of delayed completion of the Project. That will be especially so where contractual promises have been made by the Employer to other companies relying on the output date from the completed facility to be achieved.

      1 all the Engineering work is to be undertaken by others (including the Detailed Design work),

      2 all key equipment items are to be purchased directly from the Vendors by the Employer and installed under separate Subcontracts issued by the Employer,

      3 specialist services installations too are to be undertaken by Subcontractors who will be tied into Subcontracts issued by the Employer,

      4 a very reasonable time-frame for completion will be allowed, and

      5 no Guaranteed Performance Outputs of any sort are required from the Contractor.

      In a nutshell, the ‘real and present danger’ for any EPC Contractor is the actual occurrence of any one of the following four disaster scenarios on its EPC Projects, since each issue mentioned is under the Contractor's direct control:

      1 Time DisasterThe time for completion may be severely delayed due to poor management of the Engineering, Procurement, and/or Construction activities as well as the interfaces between them. This can then lead both to unrecoverable additional costs and the Contractor's income being seriously eroded due to the requirement to pay Liquidated Damages to the Employer to compensate for delayed completion.

      2 Commercial DisasterEven if the Project is completed on time, the expenditure may significantly exceed the income due to the inadequacy of the Contractor's internal controls (not only in respect of purchases and subcontracted work but also for worker productivity and wastage levels).

      3 Quality DisasterThe quality of the finished work may be well below the required standard. This could then lead to litigation over arguments as to whether or not the facility is suitable for its intended purpose. In the worst case scenario, it could lead to a complete breakdown of the facility and also involve loss of life.

      4 HSE DisasterAn untoward health, safety, and/or environmental issue may cause a severe problem that could irreparably destroy the Contractor's reputation for a good while to come, as well as being costly to remedy (or provide compensation) for the negative effects experienced.

      I have observed that far too few Contractors realise that, from the moment the Contract signing has been concluded, the Contractor has entered into the equivalent of a war zone, where time is the Contractor's principal enemy. The different ways in which time can be lost are many, some of which are almost indiscernible. Time moves along at a constant pace and is unrelenting in its progress,


Скачать книгу